Thank you for submitting your Asbestos Request Form. An Environmental Health Specialist will be contacting you soon to discuss the details of the abatement project.
Please Note:
Notification period: Once the scope of the work is defined, e.g., the bulk sample results have been received, the project manager approves the proposal, and gives authorization to abate, the contractor from our preferred vendor list will submit the legally required ten (10) working day notification to the City of Chicago Department of Public Health and other regulatory agencies based on the abatement type.
Replacement of finishes: Due to union agreements, the abatement contractor can only remove, repair, or encapsulate asbestos materials. The project manager and/or department contact managing the work is responsible for coordinating the replacement and/or repair of non-asbestos building finishes impacted during the abatement.